Week of 2019-07-28 (the 27th week)

flushing chlorine from the water line
gutter liners installed
painting the cryroom
installing the movable partitions

2019-08-04
Monday
skylight flashing
flushing chlorine water at the hydrant
temporary new water connection
gutter liners installed
ready for new hall roofing
flushing chlorine water from inside the church
critter control at the garden
ready for the first WSSC water test
painting the cryroom
Tuesday
painting the cryroom
airsoft floor pieces
installing the movable partitions
Wednesday
installing the movable partitions