back to top page2019-08-25

Week of 2019-09-01 (the 32nd week)

sound insulation in the wall
drywall in the hall
grading for the ramp

2019-09-08
Tuesday
downspouts installed
installing studs
first day of school
Wednesday
sound insulation in the wall
waterproof coating
fishing thermostat wiring
Thursday
new drywall in the hall
foam insulation on the outter wall
Friday
backfill the access ramp
backfill the foundation after waterproofing
drywall in the hall
grading for the ramp
plumbing for the AC units
outside the hall