back to top page2019-09-08

Week of 2019-09-15 (the 34th week)

sidewalk goes in
sump pump pit maintenance
drywall work

2019-09-22
Monday
the new pantry
taking out the old door
wetting down the (very dry) dirt
state of the hall
Tuesday
tamping dirt, ready for concrete
replacing broken drain pipe from front corner of roof
cleaning sump pump pits
before
after
one pit
the other pit
Wednesday
setting the door frame
mudding the drywall
the hall from the doorway
ramp area ready for concrete
ADA bathroom, ready for concrete
sidewalk area, from the hall door
drywall around the hall door ways
drywall around the windows
Thursday
ductwork in the wall
Friday
pouring concrete
ductwork in the wall
ramp ready for concrete
sidewalk forms in place
AC pad forms
smoothing concrete
sidewalk and ramp poured and curing
Saturday
ADA bathroom
access ramp
sidewalk
AC pad
drywall ready to paint
air plenum
access ramp from inside the hall
sidewalk from the hall
CCD temporary classroom area
CCD introductory session