back to top page2019-09-22

Week of 2019-09-29 (the 36th week)

finishing drywall
installing drop ceiling, light fixtures, sprinkler pipes
sprinklers in the basement

2019-10-06
Monday
sprinkler pipes in the hall
painting the prime coat in the hall
finishing drywall above the classroom partition
priming the old exterior wall of the hall
installing drop ceiling supports
removing old tile
Tuesday
outside wall primed
waiting for the outside pantry door
getting ready for the drop ceiling
Wednesday
getting ready for the drop ceiling
drywall over the former niche
compressor units ready for installation
Thursday
grading the ramp
light fixtures in place
cutting out old conduit
Friday
sprinkler pipe to the basement
lights in the ceiling grid
connecting the front downspout drain
sprinklers in the basement