back to top page2019-10-13

Week of 2019-10-20 (the 39th week)

ADA bathroom floor
hall, tiled

2019-10-27
Monday
patching the sunken floor
Tuesday
ADA bathroom, ready to pour concrete
smoothing the hall floor
repointed storage room wall
ADA bathroom floor, poured
Thursday
new doors, nave to hall
hall, tiled
light fixtures in nave, relocated and hung
hall vestibule, ready for tile
pantry electrical panel
emergency lights in the hall
Friday
new doors, nave to hall
pantry electrical panel
tile in the hall, ready for ceiling close in
hanging folding partitions
carpet to cover support columns
restriped parking spaces
Saturday
restriped parking spaces